Timeline Behind the Proposed Bond

 

The timeline behind the proposed bond is as follows:

On September 16, 2015, at the Board of Education meeting it was announced by last year's Board that we were looking into expanding.

On October 7, 2015, at the planning session there was a discussion on the project.

On October 14, 2015, a special planning session was held. An architect and our facilities manager were present and we saw the first proposed drawing.

On November 16, and December 14, 2015, Program and Priorities meetings were held. At these meetings members were asked for input on what they valued and where they felt the district needed to expand.

In December, after RFPs for architects were reviewed, two days were set aside for interviews of architectural firms.

In February, 2016, at the Board of Education meeting the Architect bid was awarded to Tetra Tech.

In early spring, Dr. Mustich spoke to each school's PAC committee and received feedback.

The Board listened, heard those who spoke and made some changes based on feedback.

At the April 6, 2016, Board of Education meeting an update was given on the project.

On May 25, 2016, at the Board of Education meeting the first video was presented showing the entire bond proposal.

On June 14, 2016, at the Planning Session, the vote was taken by the Board to put the bond up as one proposal and not as an a la carte menu. Following the planning session, at the Board of Education meeting, this decision was announced. Parents gave input at this meeting.

On June 22, 2016, I met with the PTSA Executive Committee and answered questions that they had.

On August 22, 2016, Dr. Ferraro met with the PTSA and the Booster Club parent groups to answer questions and explain the bond proposal.

Finally, On August 31, 2016, 6th grade parents were invited to a bond presentation by Dr. Mustich and Dr. Bucci while their children took a tour of the Middle School.